ertainty is sufficient if the evidence adduced enables a court to make a
fair and reasonable approximation of the damages.” Locke, 151 Ct. Cl. at 267 (citing
Stern v. Dunlap Co., 228 F.2d 939, 943 (1955)). Here, the Government failed to adduce
sufficient evidence to show that its claimed repair costs are reasonable or to allow the
Court to make a fair approximation of the damages.
The only witnesses who testified at trial regarding the amount of the
Government’s damages were Milton Schmidt and William Sanford. Mr. Schmidt is the
Chief of the Cost Section in the Corps’ Southwestern Division, and Mr. Sanford is a civil
engineering technician in the construction branch of the Corps’ Southwestern Division.
Neither witness was designated or accepted as an expert and thus, both offered lay
opinion testimony.
17 The Court arrived at this number by adding together the total costs the Government claimed for repairs
to the FY03 and FY04 dorms, as listed in paragraphs 170 and 186 of the Government’s Opening PostTrial Brief and then subtracting the costs the Government claimed for repairs to the site grading, as listed
in paragraphs 185 and 198. The Court addresses the costs associated with re-grading the site separately in
Section C below.
18 The Government concedes that it “bears the burden of proving that its costs of repair are reasonable.”
Def.’s Resp. to BPLW’s Mot. for Sum. J., Dkt. No. 97 at 14.
32
Testimony of a lay witness is admissible only upon a showing that the witness has
personal knowledge of the subject matter of the testimony. DataMill, Inc. v. United
States, 91 Fed. Cl. 722, 734 (Fed. Cl. 2010) (internal citation omitted). Federal Rule of
Evidence (“FRE”) 701, which allows a lay witness to testify in opinion form, requires the
testimony to be “rationally based on the witness’s perception.” FRE 701(a). This
requirement “effectively incorporates the personal knowledge requirement as a
prerequisite to acceptance of opinions by lay persons.” DataMill, 91 Fed. Cl. at 734-35.
The party offering the testimony must show that the witness “‘had an adequate
opportunity to observe and presently recalls the observation,’ and a ‘person who has no
knowledge of a fact except what another has told him does not satisfy the requirement of
knowledge from observation.’” Id. at 735 (quoting 1 McCormick on Evidence § 10
(Kenneth S. Broun et al. eds., 2006)). “[A] witness may testify to an event or occurrence
that he has seen himself, but not one that he knows only from the description of others.”
Id. (internal citation omitted).
1. Mr. Schmidt
The Government called Mr. Schmidt to testify regarding the Corps’ calculation of
the IGEs for the work done by Tepa LLC to repair the FY03 and FY04 dorms. The
Corps prepares an IGE to show the costs that a prudent contractor would incur during a
project, thereby ensuring that the Government does not under- or over-pay for a contract.
Tr. 1273-74 (Schmidt).
On September 11, 2008, the Corps issued an IGE for the repairs to the FY03 dorm
in the amount of $1,815,820, DX61 at 12, and an IGE for the repairs to the FY04 dorm in
the amount of $1,847,797, DX 61 at 3; Tr. 1294 (Schmidt). The Corps ultimately issued
a revised IGE for the FY03 dorm in the amount of $3,915,211, DX 56, and for the FY04
dorm in the amount of $3,608,581, DX 56A, to reflect a change in the scope of work on
the dorms, Tr. 1327-28 (Schmidt). The revised IGEs were the product of negotiations on
September 26, 2008 between Ed Morgan of the Corps and Tepa representatives, who
jointly determined that a revised scope of work was necessary. Tr. 1345, 1385-86
(Schmidt); DX 56. Based upon the revised IGEs, the Corps issued two sole-source
contracts to Tepa on September 30, 2008 for the repairs to the dorms. See DX 54; DX
57. After a subsequent modification on January 4, 2010, the total contract amounts for
the FY03 and FY04 dorms were $4,245,270.75 and $3,069,067.34, respectively. See DX
90; DX 91.
The Government relies on Mr. Schmidt’s testimony to assert the reasonableness of
its repair costs. Mr. Schmidt’s testimony, however, reveals that he lacked personal
knowledge of any of the assumptions and calculations underlying the original IGEs; the
negotiations leading to the revision of the IGEs; and the assumptions and calculations
underlying the revised IGEs. Mr. Schmidt could not provide any of the most basic
information about the assumed number of hours for the work, the number of workers
33
required, the labor rates to be paid, or the tasks to be performed. Instead, Mr. Schmidt’s
testimony consists primarily of hearsay in the form of conversations he had with Jack
Shelton and Ed Morgan, Corps employees who did not testify at trial.
a. The original IGEs
An IGE is based, in part, upon the detailed scope of work, which describes the
parameters of a given project. See Tr. 1368, 1370-71 (Schmidt). The cost estimator
takes the detailed scope of work and begins the process of pricing to arrive at the IGE.
Tr. 1371 (Schmidt). To obtain pricing information, the cost estimator relies primarily on
a computer-aided cost-estimating system called “MCACES.” Tr. 1278 (Schmidt). In
addition to MCACES, the cost estimator refers to “historical data,” a separate “H2” unit
database, and “local pricing sources.” Tr. 1290 (Schmidt). To generate an IGE, the cost
estimator makes a series of assumptions and inputs them into MCACES. See Tr. 1379
(Schmidt). The cost estimator cannot simply retrieve a number from MCACES and
insert it into the IGE. Id. Instead, it is necessary to have an experienced cost estimator,
who can compare the MCACES pricing data with local pricing data and relate that to the
construction work at hand to arrive at a sound estimate. Tr. 1289-90 (Schmidt).
Here, the detailed scope of work was prepared by someone (unknown to Mr.
Schmidt) in the Lackland Resident Office, along with the Corps’ contracting officer,
Joyce John. Tr. 1366-67 (Schmidt). Mr. Schmidt could not testify whether Ms. John or
the unknown individual determined that the work included in the detailed scope of work
was reasonable and necessary. Tr. 1369 (Schmidt).
Then, Mr. Shelton – not Mr. Schmidt – prepared the IGEs based, in part, upon the
detailed scope of work, as well as other information and documents supplied by third
parties. For example, Mr. Schmidt testified that Mr. Shelton relied on information he
gleaned from Bobbi Farrell and Ed Morgan through memos and telephone conversations.
Tr. 1372-73. As the principal preparer of the IGEs, Mr. Shelton used MCACES and the
other aforementioned resources to generate the IGEs. Mr. Schmidt conceded that he did
not know too much about the assumptions that Mr. Shelton made in generating the IGEs.
Tr. 1373-74, 1379. To the extent that Mr. Shelton could testify as to some of the
assumptions underlying the IGEs, his testimony consisted of hearsay in the form of
conversations he had with Mr. Shelton. Tr. 1379-80. The Government provided no other
evidence regarding the assumptions Mr. Shelton made in employing the databases; it did
not submit pertinent information contained in either MCACES or the H2 unit database.
See Tr. 1307-08 (Weger).
Mr. Schmidt reviewed the detailed scope of work and the IGEs prepared by Mr.
Shelton and determined that the overhead, home office, profit, and bond costs fell within
the expected ranges. Tr. 1311 (Schmidt). Based upon his past experience in costestimating, as well as a conversation with Mr. Shelton regarding the assumptions that
34
went into his estimates, Mr. Schmidt determined and certified that the costs within the
IGEs were “fair and reasonable.” Tr. 1306 (Schmidt).
Notwithstanding Mr. Schmidt’s certification, the Court finds that Mr. Schmidt
lacked the requisite personal knowledge to establish the reasonableness of the costs in the
original IGEs. It is not enough that the Government provide a witness to say that its costs
were reasonable; the Government must demonstrate that this is the case. Mr. Schmidt
could not testify regarding the rationale for including certain items in the original scope
of work, or even who created it. Likewise, he had limited knowledge as to the
assumptions and calculations Mr. Shelton made in preparing the IGEs. In fact, Mr.
Schmidt conceded that, in general, rather than his personal knowledge, he relies on others
to provide him with information, whether via emails, memos, conversations, or other
means, to determine whether an IGE is fair and reasonable. See Tr. 1365. While the
Court does not question Mr. Schmidt’s competency as Chief of the Cost Section, Mr.
Schmidt simply was not the proper witness to testify about the reasonableness of the costs
within the IGEs. The Court was not afforded “a reasonable basis of computation” when
it could not question Mr. Shelton concerning the assumptions and calculations he made
when preparing the IGEs. From the Court’s viewpoint, the cost figures provided by the
Government are simply “numbers on a page” without any substantiation or support.
b. The negotiations
The two contracts the Corps ultimately issued to Tepa were sole-source contracts,
meaning that the Corps negotiated them with Tepa and did not conduct any competitive
bidding process before awarding them to Tepa. Tr. 1382-83 (Schmidt). Ed Morgan
appears to have been the lead Corps representative during the negotiations with Tepa,
which occurred on September 26, 2008. See Tr. 1384-86. Neither Mr. Shelton nor Mr.
Schmidt was involved in the negotiations. Tr. 1344, 1391 (Schmidt). During the
negotiations, the parties decided to make certain changes to the scope of work. Tr. 1385
(Schmidt). In addition to the major changes listed above, see supra p. 12, Mr. Schmidt
testified that the scope of work changed, in part, because the parties decided to create a
tunnel beneath the dorms to do the repairs. Tr. 1328. However, as that decision was
made during the negotiations between Mr. Morgan and Tepa representatives, Mr.
Schmidt was not involved in it. Tr. 1328-30 (Schmidt).
c. The revised IGEs
As a result of the negotiations between Mr. Morgan and Tepa, and the changes in
the scope of work, the Corps issued revised IGEs for the dorms. See DX 56; DX 56A.
Again, Mr. Shelton – not Mr. Schmidt – prepared the revised IGEs. Tr. 1382, 1390-91
(Schmidt). Mr. Shelton prepared the revised IGEs based upon information regarding the
negotiations given to him by Mr. Morgan. Tr. 1391 (Schmidt). Specifically, Mr. Shelton
relied upon a price negotiation memorandum, which included information regarding the
35
increased duration of the project and the addition of the site grading option. See Tr.
1337-41 (Schmidt); DX 87; DX 92.
Because Mr. Shelton prepared the revised IGEs, Mr. Schmidt could not testify as
to the information that Mr. Shelton put into MCACES to generate the costs in the revised
IGEs. Tr. 1393 (Schmidt). Mr. Schmidt conceded that he did not calculate the numbers
written into the revised IGEs, those on the IGE summary page, or even the total contract
price. Tr. 1389. Mr. Schmidt did not participate in the analysis for arriving at the
$50,000 figure for removal costs. Tr. 1387 (Schmidt). He assumed the costs for the
structural and geotechnical engineers were added together to come up with the $15,000
figure in the revised IGEs, Tr. 1388-89 (Schmidt), and likewise, appeared to assume that
the geotechnical and structural testing costs were included in the $115,000 figure for
“AM” costs, Tr. 1353-54 (Schmidt). Mr. Schmidt testified that the unit costs in the IGEs
were Mr. Morgan’s figures from the unit price database, but he could not testify
otherwise regarding how the unit prices were determined. Tr. 1393-94 (Schmidt). He
also could not testify as to whether Tepa subtracted costs from its overhead for savings
due to the project being onsite. Tr. 1396 (Schmidt). Mr. Schmidt could not even break
down the details of the revised IGEs to explain what portions were his work product or
that of Messrs. Morgan or Shelton. Tr. 1392-93 (Schmidt).
Mr. Schmidt was able to identify and break down some of the costs within the
revised IGEs, such as the labor costs for the project superintendent, equipment costs for
pickup trucks, direct costs to rent an office trailer, and a Storm Water Pollution
Prevention Plan. See Tr. 1346-53 (Schmidt). As detailed above, however, there were
significant gaps in his knowledge of the calculations and assumptions underlying the
figures in the revised IGEs. Despite the gaps in Mr. Schmidt’s knowledge regarding the
assumptions underlying the revised IGEs, he approved them, Tr. 1392 (Schmidt),
certifying that the costs contained therein were “fair and reasonable,” Tr. 1362-63, 1374
(Schmidt). Mr. Schmidt approved the revised IGEs based upon his conversations with
Mr. Morgan, a copy of the original IGEs marked up by Mr. Morgan,
19 a price objective
memorandum and a price negotiation memorandum, and copies of the revised IGEs
provided to him by Mr. Shelton. Tr. 1343, 1346, 1360, 1383-85 (Schmidt); DX 87; DX
92.
On the whole, the weaknesses in Mr. Schmidt’s testimony render it woefully
insufficient to allow the Court to assess whether the costs reflected in the revised IGEs
are reasonable. As an initial matter, the Court questions whether the revised cost
estimates were truly “independent.” Mr. Schmidt conceded that as part of the
19 Mr. Schmidt’s testimony indicates that the numbers in the original IGEs were crossed out and revised
numbers were written in, see Tr. 1388-89 (Schmidt), seemingly by Mr. Morgan as a result of his
negotiations with Tepa, see Tr. 1390 (Schmidt).
36
determination of whether costs are fair and reasonable, the cost estimator does not
consider the method of contracting. Tr. 1290, 1383. This is particular noteworthy
because the Corps made significant upward adjustments to the IGEs after the price
negotiations with Tepa. After incorporating the revisions, the total amounts of the IGEs
for the FY03 and FY04 dorms increased from $1,815,820 and $1,847,797 to $3,915,211
and $3,608,581, respectively. Compare DX 61 at 12, with DX 56, and DX 61 at 3, with
DX 56A; see also Def.’s Br. ¶¶ 133-34, 141-42. Because the awards to Tepa were solesource contracts, without any competitive bidding, the Court cannot assume the
reasonableness of the contract prices.
Moreover, the second- and third-hand character of Mr. Schmidt’s testimony makes
it largely unhelpful. Because Mr. Schmidt was not involved in the negotiations leading to
the revisions, he could provide only a second-hand description of the changes in the
scope of work, rather than details concerning the negotiations and how the decisions to
alter the scope of work were made. Likewise, Mr. Schmidt did not prepare the revised
IGEs, so he could not testify as to the calculations and assumptions underlying them. It is
evident that Mr. Schmidt’s testimony is not based upon his own personal knowledge. As
a result, it cannot serve as a predicate for a determination that the Government’s repair
costs were reasonable.20
See DataMill, 91 Fed. Cl. at 734 (noting that where a witness
testifies on matters “with which he has no familiarity,” it is “of no use to the trier of fact
and . . . waste[s] everybody’s time.”) (internal citations omitted).
2. Mr. Sanford
Mr. Sanford, who had been tasked by the Corps with determining which costs
associated with Tepa’s repair work were attributable to BPLW, Tr. 1607 (Sanford),
testified about his work at trial. However, as with Mr. Schmidt, testimony, the Court
finds Mr. Sanford’s testimony of marginal utility.
To make his determination, Mr. Sanford primarily relied on the Tepa contracts but
also considered the government estimates. Tr. 1607, 1623 (Sanford). He then created a
memorandum, identifying the costs he deemed attributable to BPLW. Tr. 1650-51
(Sanford); DX 71. The costs included those for: designing a crawl space; excavating
beneath the dorms to remove the broken piping and replace it with a new piping system;
metal to hang the pipe; replacement of the piping; electrical work; Tepa’s labor burden;
Tepa’s home office overhead; Tepa’s profit; Tepa’s builders’ risk insurance and general
liability insurance; Tepa’s bond costs; final as-built drawings; shower pans; site work;
curbing; and metals. See Tr. 1653-63 (Sanford); DX 71.
20 Insofar as the Government relies on Mr. Schmidt’s testimony to establish the reasonableness of its
costs to remedy the site grading, the Government has not only failed to show that BPLW’s design caused
the improper site grading, see infra Section C, but it also has failed to establish that the damages it claims
for the site grading are reasonable.
37
BPLW makes much of the fact that Mr. Sanford is not a plumbing engineer and
had no role in determining whether BPLW was liable for the repair costs, as that
determination was made by a separate board. See Pl.’s Br. 89-90; Tr. 1672-75 (Sanford).
On those bases, BPLW maintains that Mr. Sanford is unqualified to decide which costs
should be attributable to BPLW. See Pl.’s Br. 89-90. The Court merely views Mr.
Sanford’s testimony on that front as duplicative of its own responsibility to determine
which costs are attributable to BPLW due to its negligent designs. The Court finds Mr.
Sanford’s testimony deficient for another reason: as with Mr. Schmidt, Mr. Sanford’s
testimony does not aid the Court in determining whether the amounts paid to Tepa for the
repair work were reasonable.
Mr. Sanford essentially reviewed the Tepa contracts and allocated component
costs to BPLW based upon a board’s determination that BPLW was liable for certain
damages. Tr. 1677-79 (Sanford). Like Mr. Schmidt, however, Mr. Sanford was not
privy to the negotiations, which resulted in the revised IGEs and ultimately, the contract
awards to Tepa. Tr. 1682 (Sanford). Mr. Sanford did not assess whether the work within
the detailed scope of work was reasonable or necessary. Tr. 1683 (Sanford). Moreover,
Mr. Sanford did not observe any of the repair work being done by Tepa. Tr. 1680-81
(Sanford). Accordingly, he had no knowledge regarding whether the repair work by
Tepa conformed to the scope of work. Tr. 1683 (Sanford).
In sum, through the testimony of Mr. Schmidt and Mr. Sanford, the Government
provided insufficient evidence to show that its repair costs were reasonable. As such, the
Government has failed to show that it is entitled to the damages it claims for the repairs
associated with the replacement of the piping system and the remedial site grading.
C. Costs to Remedy the Inadequate Site Grading
The Government has shown that BPLW provided a negligent civil site grading
design insofar as the design failed to meet the slope requirements set forth in the soils
reports and the AEIM. As a result, the Government seeks reimbursement for $340,592 of
the costs it paid for remedial work to the site grading. See Def.’s Br. ¶¶ 185, 198. The
Government contends that BPLW is liable for its deficient site grading design regardless
of how the grades were ultimately constructed. See id. ¶ 108. The Government
maintains that “even if it were true that the construction contractor failed to grade the site
in accordance with BPLW’s design, it does not relieve BPLW of liability for failing to
produce a civil site grading design that complied with the Soils Reports and AEIM.” Id.
The Court disagrees.
As noted above, in addition to showing that BPLW breached the Contract, the
Government must show that BPLW’s breach caused the alleged damages. See San
Carlos Irrigation, 877 F.2d at 959. As this Court has stated, “design compliance is ‘an
38
essential element’ in evaluating a claim for ‘negligently preparing defective plans and
specifications.” C. H. Guernsey, 65 Fed. Cl. at 596 (internal citation omitted). If a
claimant cannot show that the contractor actually complied with the purportedly
negligent design, it cannot show that the design caused the damages alleged.
By its own admission, the Government cannot show that CF Jordan initially
constructed the grades in accordance with BPLW’s design and thus, that the negligent
design led to the improper grades and pooling of water. See Def.’s Br. ¶ 109. The
Government has no as-built data to show how CF Jordan initially constructed the grades,
see Tr. 2426-27 (Helmer), and no witnesses testified as to the as-built condition of the
site grading, see Pl.’s Resp. 18; Def.’s Rep. 30. As the Government notes, while CF
Jordan completed dorm construction in August 2005 and November 2006, the earliest
report concerning the site grading—Ng’s report—was based upon a topographical survey
conducted in late 2007. See Def.’s Rep. 30 n.7 (citing DX 45 at 3). Mr. Long did not
visit the site until November 2007, and Mr. Helmer did not visit the site until 2009. Id.
Given the lack of information regarding the as-built grades, the Government takes the
position that “the Ng data shed no light on whether the construction grades matched the
design grades because the grades may have changed after construction due to soil
movement.” Def.’s Br. ¶ 109 (citing Tr. 1233 (Leathers)). While the Court questions
whether the grades could have changed so drastically over a one- to two-year period, the
fact remains that the Government cannot carry its burden to show that CF Jordan
complied with BPLW’s design.
In contending that contractor compliance is irrelevant, the Government
emphasizes that “in many locations the actual grades by Ng were steeper than those
called for in BPLW’s design.” Id. At trial, Mr. Leathers provided support for this view.
Specifically, based upon data from the Ng’s report, he found that all six points measured
around the FY03 dorm revealed grades at steeper slopes than that stipulated in BPLW’s
designs. Tr. 991 (Leathers). Of the seven survey points around the FY04 dorm, Mr.
Leathers found that four were steeper than those called for in BPLW’s designs, while
three were the same or less. Tr. 992 (Leathers). Overall, after reviewing the Ng survey
data, Mr. Leathers concluded that the slope at the majority of locations (10 of 13) around
the dorms was steeper than those called for in BPLW’s site grading design. Tr. 992-93.
Nevertheless, as noted, the Ng data was obtained more than two years after CF
Jordan constructed the dorms. The Government itself undercuts the relevance of the Ng
data by maintaining that the grades could have shifted over that two-year period.
Moreover, Mr. Leathers’ testimony shows that there were at least some locations where
the slope was not as steep as that called for in BPLW’s design. If the Government seeks
to have the Court rely on the Ng data where it suggests that CF Jordan more than
complied with BPLW’s site grading design, the Court also must rely on the Ng data
where it suggests that CF Jordan failed to comply with BPLW’s site grading design.
39
Finally, although the Court does not have before it definitive data regarding the asbuilt condition of the site grading, the weight of the evidence suggests that CF Jordan
constructed the grades at a slope flatter than that provided for in BPLW’s civil site
grading design. It is undisputed that BPLW’s site grading design called for “positive
slope” around the perimeter of the dorms. See Def.’s Br. ¶ 107 (citing Tr. 1233
(Leathers)). Yet, multiple witnesses testified to the fact that they observed ponding and
pooling of water in the area surrounding the dorms.21
See Tr. 821 (Long) (testifying that
when he visited the site, in late 2007, he observed pooling around the FY04 dorm); Tr.
599 (McCleskey) (same). Mr. Leathers conceded that where there is pooling of water, “it
means that . . . there is not positive drainage.” Tr. 1233. Again, while there is no
definitive evidence of the as-built grades, the weight of the evidence indicates that CF
Jordan failed to comply with BPLW’s site grading plan. In fact, while the Government
appears to have backed away from its earlier stipulation, it initially stipulated that “CF
Jordan failed to grade the site with positive grading and drainage to carry water away
from the building.” Stip. ¶ 25.
Based upon the foregoing, the Government has not shown that CF Jordan
complied with BPLW’s site grading design and thus, that it was BPLW’s negligent
design, rather than CF Jordan’s improper site grading, that caused the ponding and
pooling of water that contributed to the soil heave. As such, the Government cannot
recover the costs it claims for remedying the inadequate site grading.
D. Costs to Implement the Modifications to BPLW’s Underfloor Piping Design
Lastly, the Government seeks reimbursement for the $197,596.47 it spent to
implement BPLW’s modified piping design. Def.’s Br. ¶ 117. As set forth above, after
BPLW’s mechanical engineers “discovered” that the soils beneath the dorms had a high
“shrink swell potential,” it informed the Corps that it would need to modify its design.
PX 22. Mr. Bray confirmed that BPLW recommended the modifications that the parties
ultimately adopted. See Tr. 2347-49, 2351-52. Thereafter, the Corps provided CF Jordan
with immediate funds and a notice to proceed in order to avoid additional costs associated
with construction delays. Def.’s Br. ¶ 116; DX 28; PX 27 at 2; PX 70 (P00003).
It is undisputed that it was BPLW’s responsibility to provide the underfloor piping
design for the project. See Stip. ¶ 7. It is also undisputed that BPLW was required to
provide a design complying with the soils reports, which found that the soils beneath the
dorms had “a very high shrink swell potential.” Stip. ¶¶ 11, 17. The evidence indicates
that BPLW initially failed to use any means to accommodate the expansive soils because
the fact that the soils were highly expansive “slipped past” BPLW’s mechanical
21 The Government also stipulated to the fact that “CF Jordan allowed post-rain ponding and pooling of
water around the foundation perimeter during construction.” Stip. ¶ 23.
40
engineers. PX 22; Tr. 2375 (Bray). Upon realizing its oversight, BPLW suggested
modifications to accommodate the expansive soils. See PX 22.
As a result, the Government incurred additional costs to pay for the more
expensive cast iron pipe and the new pipe layout. See PX 28 (estimating a price
difference of $173,201—not including CF Jordan’s overhead and profit—for the new
layout and use of cast iron pipe, which the contractor estimated to be three times the cost
of PVC pipe). While the Government may have received a higher grade piping system as
a result, BPLW still failed to provide a non-negligent design. The Government suffered
damage—in the form of increased costs—for a piping system that continued to be
negligently designed. Essentially, BPLW’s negligence caused the Government to
needlessly incur these costs because the changes had no material effect on improving the
design. These costs are recoverable.
Moreover, the Government’s damage claim for the increased costs is reasonable.
Based upon the communications between Mr. Bray and Ms. Farrell, it is apparent that
BPLW viewed the changes as necessary modifications of its design. See PX 22. In
addition, given that BPLW recommended the means by which to modify its design,
BPLW must have viewed the means as reasonable. See id.; Tr. 2347-49, 2351-52 (Bray).
Lastly, by providing CF Jordan with immediate funds and issuing the notice to proceed,
the Government made reasonable efforts to mitigate damages that could have increased
on account of delays. See DX 28; PX 27 at 2; PX 70 (P00003). Based upon the
foregoing, the Court concludes that the Government is entitled to the $197,596.47 in
costs it incurred to implement the modifications to BPLW’s design.
Conclusion
As set forth above, the Government has shown that it is entitled to recover the
costs it incurred to implement the modifications to BPLW’s piping design. The
Government is not entitled to recover the costs associated with the repairs of the broken
pipes; the replacement of the underfloor piping systems; or the re-grading of the site.
Pursuant to Rule 54(d), BPLW as the prevailing party is entitled to recover its reasonable
costs.
IT IS SO ORDERED.